On September 10, George J. Meyers Swimming Center, 7900 Carr Drive, reopened after its annual shutdown from September 3-9. Staff accomplished a multitude of tasks, in addition to a thorough deep cleaning throughout the facility:

  • Drain pool -partial drain, refill, balance, heat
  • Replacement work of “T” fitting in circulation system (done by BTS – contractor and JD)
  • Clean/degrease diving board structures; Complete diving board inspection – all boards
  • Remove and install new diving board
  • Reseal deck-to-gutter seam/caulking on east and west ends
  • Refinish west end lobby
  • Repaint floor in classroom and guard room
  • Vacuum out overhead air vents in locker room/lobby areas

The results are looking great and the pool is ready for the cooler season ahead! For operating hours and information on Meyers Pool, visit https://apexprd.org/facility/george-j-meyers-swimming-pool