Bond Project Status

Apex Park and Recreation District 2016 Bond Projects

On Tuesday evening, May 3, 2016, Apex Park and Recreation District announced preliminary results for the mail ballot election. Voters approved the ballot question proposing the renovation/expansion/construction of six facilities in various locations around the district.

14,294 voted yes on Issue A and 9,199 voted no – passing the bond issue to renew the existing $25 million Apex Center bond for 20 years. Ballots were mailed to more than 80,000 active registered voters of Apex Park and Recreation District.

For more information, please contact Katie Groke Ellis at 303.463.4270 or KatieG@ApexPRD.org.

At its regular January 5 meeting, the Apex Park and Recreation District board of directors approved vendors for all six of the district’s upcoming bond projects. Read more here.

Construction Notices

The voter-approved improvements to the Apex Tennis Center are now underway: renovating the eight outdoor courts with post tension surfaces, adding new lights and fences, and adding four new indoor courts and controlled access to all areas of the Apex Tennis Center.

During the construction process, the Apex Tennis Center outdoor courts are closed but we’ll offer the full range of tennis activities by making use of the other tennis courts throughout the district, and our building remains open during business hours for stringing, pro shop sales and general info. The planned reopening of the outdoor courts is scheduled for late summer, with a date to be announced later. For questions about programs, leagues, and alternative courts, please contact Michele at 303.420.1210 or MicheleC@ApexPRD.org.

The bond will fund the following projects

Secrest Center

6820 W. 66th Ave.

Construct 21,521+ sq. ft. replacement recreation center to include small weight room, community/aerobics area teen center, small gym, locker rooms, warm water wellness pool. Swimming pool and inline hockey rink will remain.

Estimated Complete Date: Summer 2018

Fitzmorris Recreation Center

Independence St. and W. 62nd Pl.

Construct 8,500+ sq. ft. recreation center, six-lane pool to include small weight room, community/aerobics area.

Estimated Complete Date: Summer 2018

Apex Tennis Center

6430 Miller Street

Renovate eight outdoor courts with post tension surfaces, new lights, fences. Addition of facility with four new indoor courts and controlled access to all areas of the tennis complex. 

Estimated Complete Date: Outdoor courts opening fall 2017 and indoor courts opening winter 2018

Lutz Sports Complex Improvements

10664 W. 58th Ave.

Construct a new four-field baseball/softball pod complex with lighting, parking, restroom/concession.

Estimated Complete Date: Summer 2018

Apex Center – Renovation, Splash Pad Addition

13150 W. 72nd Ave.

Construct 7,800 sq. ft. outdoor splash pad, renovate aquatics area center pool, renovate indoor playground.

Estimated Complete Date: Splash pad and indoor pool: winter 2018. Indoor playground: summer 2018

NOTICE: Construction to improve the Apex Center indoor Middle Play Pool will be finished in late December. The Middle Play Pool will be closed during that time but the rest of the facility will be open as usual. For updated closure information, or to learn more about alternative party packages and rentals, stop by Guest Services or call 303.424.2739.

Long Lake Ranch Regional Park Improvements

Construct two new baseball/softball fields, including backstops, to complete the first five-field complex, lighting for all five baseball/softball fields; construct a restroom/concession building. Construct two new synthetic multi-sport turf fields (lacrosse/rugby/football), with parking and lights. 

Estimated Complete Date: Summer 2018